Status |
Start
Date
|
|
|
|
|
|
|||||
| Site Goals | 9/29/00 | 10/11/00 | All | Donor / Volunteer Driven | |
| Branding Message | 9/29/00 | 10/11/00 | All | ||
| Target Audience | 9/29/00 | 10/11/00 | All | ||
| User Scenarios | 9/29/00 | 10/9/00 | All | ||
|
|
|||||
|
Initial
acquisition of information
|
|||||
| Staff Bio | 9/29/00 | 10/11/00 | Eddie | Last Bio Received 12/7/00 | |
| Partners Info | 9/29/00 | 10/11/00 | Eddie | ||
| Program Info | 9/29/00 | 10/11/00 | Annie, Linden, Ted | ||
| Special Events | 9/29/00 | 10/11/00 | Charise, Annie, Linden, Ted | ||
| Art work | 9/29/00 | 10/20/00 | All | ||
| Photos | 9/29/00 | 10/20/00 | All | ||
| Review of other missing content with client | 9/29/00 | 12/1/00 | All | Last Content Received 12/7/00 | |
|
Information
architecture
|
|||||
| Initial Site Map | 9/29/00 | 10/6/00 | Eddie | ||
| Finalize site map with client | 10/11/00 | 10/11/00 | All | Site map approved by client and site architecture finalized. | |
| Story boards for pages | 10/11/00 | 10/20/00 | All | Time constraints kept us from developing site storyboards for each page. | |
| PHASE 1:Text only site | 10/20/00 | 10/27/00 | All | Client determined that text only site was not required - content not ready by 10/27/00 | |
| Acquisition of any other content from client | 10/11/00 | 10/20/00 | All | Continuing to receive content from Client | |
| Finalize content layout with client | 10/11/00 | 10/27/00 | All | ||
| Start Full Graphics Site | 10/20/00 | 11/24//00 | All | Final Graphics site completed 12/8/00 | |
| PHASE II: text only site | 10/27/00 | 11/10/00 | All | Client determined that text only site was not required - content not ready by 10/27/00 | |
|
|
|||||
| Obtain colors and style preference | 9/29/00 | 10/11/00 | Annie | ||
| commence style guides | 10/11/00 | 11/24/00 | Annie, Ted, Charise | ||
| Round 1 of comps and navigation scheme | 10/2/00 | 10/11/00 | All | ||
| assignment of images to pages | 10/11/00 | 11/24/00 | All, picture assignments completed by team member who is responsible for those pages. | Image acquisition is a continual process and is updated periodically with new images | |
| Show client first comps and inner pages | 10/11/00 | 10/11/00 | All | ||
| feedback from client round 1 comps | 10/11/00 | 10/12/00 | All | Annie will be client liaison for design comps in future rounds. | |
| Scanning and color adjusting photos/artwork | 10/11/00 | 11/10/00 | All, picture assignments completed by team member who is responsible for those pages. | ||
| Take pictures of staff and Halloween party | 10/11/00 | 10/27/00 | Annie, Ted | Pictures taken and posted to shared folder under Family Connections Project | |
| round 2 of comps & navigation scheme | 10/12/00 | 10/19/00 | All | Client requests redesign of home page. | |
| Show client second comps | 10/19/00 | 10/19/00 | |||
| approval from client round 2 comps | 10/19/00 | 10/20/00 | |||
| final acquisition of artwork/photos | 10/31/00 | Final acquisition of artwork 12/07/00 | |||
| scanning of photos artwork | 11/17/00 | All | |||
| finalization of assignment of images to pages | 11/17/00 | All | Image assignment not finalized until the actual building of pages | ||
| finalize design of inner pages | 11/17/00 | ||||
|
|
|||||
| alpha site (20%) | 11/22/00 | 11/27/00 | All | Secondary and Tertiary Navigation pages finalized by the client. | |
| Finalize links | 10/20/00 | 11/27/00 | All | Navigation is finalized and posted to the style guide. | |
| alpha testing | 10/27/00 | 11/27/00 | All | ||
| beta site (100%) | 11/27/00 | 12/8/00 | All | ||
| beta testing | 11/27/00 | 12/8/00 | Beta testing to continue 12/9 and 12/10/00 | ||
|
|
|||||
| Preparation for project review | 12/4/00 | 12/8/00 | Preparation for Project Review to continue 12/9 and 12/10/00 | ||